Technical room ready

On the previous trip we had installed a temporary roof on the technical room to allow the electrician to connect up the fuse box with the mains. However, I have actually got back out before that has been done and have completed the final roof, as seen in the following…

Continue reading

Pool house exterior finished

A couple of weeks over Easter back out in France and a chance to check on the progress of the pool house. The following photos show the progress made during our time in France, with the stone quoins and lintel being installed and then a white monocouche (render) being put…

Continue reading

Plumbing finished…

Well nearly… The pipes from the pool and into the technical room have now been connected and the remainder of the plumbing within the technical room completed. This work included the installation of the other two pumps and the filter cartridge unit. We opted for a cartridge system, as we…

Continue reading

Back out in France

We’ve managed to grab a couple of weeks out in France over the Easter holiday, so can see the progress made on the pool house and the rendering of the pool walls. There is about another days’ work on the pool floor and walls before it is ready for the…

Continue reading

Beam supports removed…

Quite some effort to remove the supports from under the cast beams that go across the deep end of the pool. There were 10x100mm blocks under the shuttering to support the formwork whilst the beam was being cast, resulting in several tonnes of force being exerted on the blocks; nothing…

Continue reading